CHANGE ORDER NUMBER 1
Pursuant to that agreement between George Washington, described
herein as OWNER and Monticello Roofing, described herein as
CONTRACTOR, dated April 1, 1995 the following change is made in
the specifications and scope of work to be performed:
replace standard flashing with heavy gauge flashing
This results in a increase of the total contract price in the
amount of $ 200.00 ( two hundred & no/100 dollars) and an adjusted
total contract price of $ 9,560.00 ( nine thousand five hundred
sixty & no/100 dollars.)
Dated: _______________________________________
Accepted by:
______________________________________________________
George Washington, OWNER
______________________________________________________
Monticello Roofing, CONTRACTOR